A basic cleaning of the station was done on July 17, 2009 by Monica Rojas. Copper screens were corroded and need to be change.
A basic cleaning of the station was done on August 28, 2009 by Wesley Merten and Stephanie Williams from 13:30pm to 14:30pm. All of the screens need to be replaced. There was considerable biofouling on all stations, and the main pole towards the top was pretty encrusted with barnacles, oysters, and clams.
On Friday the 18th Katie Flynn and Wesley Merten did a complete clean of the CREW station. All lines, cables, chains, and shackles were cleaned and inspected. Things are showing signs of wear. For instance, the outer housing on the shallow radiometer is beginning to deteriorate. Also, there area few lines that travel around the circumference of the main spar that are loose. Calibration CTD was deployed from 10:07am to 1:37pm.
This site is for recording maintenance records of the La Parguera Marine Reserve NOAA ICON/CREWS station for data management purposes. Please update this blog whenever new operations are performed in the field, so that NOAA/AOML can coordinate data management efforts with the La Parguera ICON/CREWS station field efforts.
Tuesday, September 22, 2009
Monday, July 13, 2009
Cleaning June - July 2009
A complete cleaning (CTD validation, cleaned all instruments, chains, lines, and tower) at the CREWS Station was done June 8, 2009 by Francisco Soto and Mónica Rojas.
The validation CTD was placed at 7:55am and was removed at 11:15am.
Basic cleaning of the station was done on June 25th, July 2nd and July 9th, 2009 by Mónica Rojas.
The validation CTD was placed at 7:55am and was removed at 11:15am.
Basic cleaning of the station was done on June 25th, July 2nd and July 9th, 2009 by Mónica Rojas.
Monday, June 08, 2009
Cleaning update June 8, 2009
A basic cleaning of the station was done on May 21, 2009 and on June 3, 2009 by Francisco Soto.
Monday, May 18, 2009
Cleaning update May 18, 2009
A complete cleaning (CTD validation, cleaned all instruments, chains, lines, and tower) at the CREWS Station was done May 14, 2009 by Francisco Soto and Diana Beltrán.
The validation CTD was placed at 7:55am and was removed at 10:10am.
A basic cleaning was done on April 17th and April 29th, 2009 by Francisco Soto.
The validation CTD was placed at 7:55am and was removed at 10:10am.
A basic cleaning was done on April 17th and April 29th, 2009 by Francisco Soto.
Tuesday, April 14, 2009
Cleaning update April 12, 2009
A complete cleaning (CTD validation, cleaned all instruments, chains, lines, and tower) at the CREWS Station was done March 25, 2009 between 9:10 and 9:55am by Francisco Soto, Stephanie Williams and Suhey Ortiz.
The validation CTD was placed at 7:30am and was removed at 11:20am.
A basic cleaning was done on april 3, 2009 by Francisco Soto and Stephanie Williams.
The validation CTD was placed at 7:30am and was removed at 11:20am.
A basic cleaning was done on april 3, 2009 by Francisco Soto and Stephanie Williams.
Tuesday, March 03, 2009
Update February 2009
Basic cleanings of the CREWS station in La Parguera, Puerto Rico were performed on February 12 and February 27, 2009 by Francisco Soto and Jorge Casillas.
Copper screens and zincs were replaced.
Copper screens and zincs were replaced.
Wednesday, February 25, 2009
Update November 2008
Basic cleanings of the CREWS station in La Parguera, Puerto Rico were performed on November 10 and November 17, 2008 by Francisco Soto and Diana Beltrán.