This site is for recording maintenance records of the La Parguera Marine Reserve NOAA ICON/CREWS station for data management purposes. Please update this blog whenever new operations are performed in the field, so that NOAA/AOML can coordinate data management efforts with the La Parguera ICON/CREWS station field efforts.
Wednesday, September 05, 2007
Cleaning Updated August 31
The validation CT was installed at 7:50am and removed at 11:15am. The station was cleaned between 9:05 and 9:55am.
No particulars were observed.
Wednesday, August 15, 2007
Maintenance Update
A complete cleaning of the CREWS station in La Parguera, Puerto Rico was performed on August 10, 2007 by Wess Merton, Stephanie Williams and Katie Flynn.
The validation CT was installed at 8:45am and removed at 12:00pm. The station was cleaned between 10:05 and 11:30am.
The optical sensors of the radiometers were cleaned, there is some calcareous algae overgrowing such sensors.
The CTDs were cleaned and three of the copper screens were replaced, the fourth remains inaccessible.
Friday, May 25, 2007
SAMI pCO2 Re-installed
Jim
Thursday, May 17, 2007
Update on BICs, SAMI
Chris Langdon
Maintenance Log
Here is a small table of when/what for the CREWS.
Francisco
2/1/2007, Complete, CTD validation
2/15/2007, Basic, Cleanded algal growth on chains, and mainframe
3/5/2007, Complete, CTD validation
3/13/2007, Basic, cleaned and examined all gauges, stantions, and chain links
3/27/2007, Complete, CTD validation, need screens
4/17/2007, Basic, cleaned algal growth on chains, and mainframe
5/2/2007, Complete, CTD validiation, changed 3 of 4 screens
5/15/2007, Basic, cleaned algal growth on chains, and mainframe
Monday, May 14, 2007
Samples for Ocean Acidification Studies Taken
On 5/14/07 the BIC sensors were observed to be heavily fouled. I cleaned
both.
Water samples for TA, DIC and O2 were collected on 5/14. 5/15, 5/16, 5/17 and 5/18. These data indicate that the SAMI was reading high by 84 uatm before the change of chemicals on 5/16/07.
Jorge's SeaCat CTD was profiled at the stick on 5/15 and 5/18.
The AOML water sampler was deployed at the stck on 5/17 and 5/18 and collected twelve good samples. Unfortunately the SAMI was not operational that the time.
Chris
Tuesday, April 24, 2007
Maintenance Update
Francisco